Town Manager’s Report to Mayor and
Town Council
October 17, 2011
Bids on Replacement of Roofs at Water
Treatment Plant and Pump Station at Hot
and
Cold Tanks
As I discussed at the October 6
meeting, we are taking bids on the roofs at the water treatment plant building
itself and at the High Level Pump Station at the Hot and Cold Tanks. The pre
bid on the tank will be on Friday, October 14 at 10:00 and the bid will be
received at the town Hall on Thursday, October 20, 2011.
We have budgeted for this roof
replacement in this year’s budget. This money will come out of the water escrow
fund, therefore having no direct effect on the cash flow. In the interest of
getting this project moving before the advent of the cold weather months, I am
going to request that Council allow the Water and Finances Committees to
approve the bids at a meeting after the October 20 bid opening. I want to do
this because the next scheduled meeting of the Council will not be until
November 7, three weeks after October 17.
I think that if we wait until November 7 to approve the bids it will
jeopardize having the project done this Fall and could possibly push the
project into next Spring. We had planned to get the project done this Fall so
the new roofs could be installed before the winter.
Scheduling of Flu Vaccinations
You have in your agenda packet an
October 10, 2011 memo from Purchasing Agent Billy Hamm. In the memo he give the
date and time of the flu vaccine shots. The flu shots are offered to all Town
of Marion employees, all members of the Marion Life Saving Crew and all members
of the Marion Volunteer Fire Department.
We are going to do it a little
differently this year. In the past we have utilized both the Health Department
and Virginia Department of Health at around $25 per shot. This year we talked
to Rite Aid Drug Store here in Marion and they can do it a little differently
and this process will be
cheaper to the town. Almost all town
employees carry town provided health
insurance. For those employees the
shot will be charged directly to the insurance company with no direct cost to
the town or them. For all town employees who do not carry town insurance, their
carrier will be charge the $27 fee. If their insurance does not pick up that
cost then town will then pick it up for them. The same goes with the Fire
Department and Rescue Squad. If the individual’s health plan will not pick up
the cost the town will pick it up. We normally administer about 75 shots each
season.
New Brush Pickup Schedule and Fall
Leaf Pickup Schedule
You have in your agenda packet two
documents. One is the schedule leaf pickup for this Fall and the second is the
new brush pickup schedule.
Concerning the new brush schedule, we
are now in the stage where we pick it up brush only once a month. The brush
will be picked up the week of the fourth Monday beginning October 24. For the
remainder of 2011 brush and bagged grass will be picked up the week of November
28 and December 26. Brush will be
picked up on the same day as the garbage is picked up
that week. As always brush can only
be removed that is three inches or smaller and no more than six feet in length.
Concerning the leaf schedule, we will
be using the same plan that we have used successfully the past eight or so
years. We again have sectioned the town into three zones with North Main
Street, Chatham Hill Road and South Main being the dividing lines. We will
begin in Zone 1 which is the northeast corner of town bounded by Chatham Hill
Road and North Main Street. It will be picked up the weeks of October 24,
November 14 and December 5. Zone 2 is the northwest zone of town and is bounded
by Main Street and Chatham Hill Road. It will be picked up the weeks of October
31, November 21 and December 12. Zone 3 is the southern zone of town bounded by
the Main Streets. It will be picked up November 7, November 28 and December
19.
Digester Biogas Project Update
We met with the contractor, Frizzell
Construction, for the biogas project on October 6 with mixed results. At the
meeting were representatives of Frizzell Construction, the low bidder on the
project, and several members of our engineering and sewer treatment plant staff.
We were meeting to try to find cost savings in their bid that came in over
$200,000 over the engineer’s estimate.
Bids Items 1 and 2, for the
cogeneration unit to the dewatering building and for the mixing unit,
respectively, were fairly close to the engineer’s estimate, at nine percent and
23% over. However, Item 3 for all the
piping was over by a substantial factor. At the October 6 meeting we tried to
get a cost break on that item but the contractor was not willing to give very
much. He stated that that had thrown a variety of their costs elements into this line item and that it could not be
deemed as piping only.
On the positive side, extra money may
be available to run electrical to the influent pump station our engineers,
Thompson and Litton, reported at the meeting. Our engineering and sewer
treatment staffs were very excited about this. Our electric bill has
historically been around $2,500 per month for the pumps and by running the
service from the cogeneration unit approximately 90% plus of that costcould be
saved by the town.
I had asked for Thompson and Litton
to get all the cost increases, costs saving, cost / benefit analysis,
additional funding scenarios together for the October 17 meeting. However, upon
on talking and contacting them on several occasions, I found that Frizzell
Construction had not gotten them enough information to make accurate
determinations / recommendations.
Accordingly, that information will be
provided for Council at its November 7th meeting. At that meeting
Council will be presented with a recommendation to move on with the current
contractor or to rebid the project. We have until on or about November 30 to
accept or reject Frizzell Construction’s Bid, a provided in the 90 contract
window. Bids were received on
August 31.
Respectfully Submitted,
John E. B. Clark, Jr.
Town Manager