Town Manager’s Report to Mayor and
Town Council
September 19, 2011
Mt. Rogers Planning District
Commission (PDC) grant award for Meter Replacement
You have in your agenda packet a August 30, 2011 letter from Mt. Rogers PDC Executive
Director Dave Barrett notifying the town of Marion that we were the recipient
of a $40,500 grant from the Southwest Virginia Regional Water and Wastewater
Construction Fund. I had applied for this grant in July. I believe the fund had
approximately $400,000 in it from both federal and state sources.
The grant is for the first year of
the five year meter replacement program, which we budgeted for this fiscal
year. The grant requires a 50% / 50% match and the $50,000 we allocated for
this fiscal year will meet that criteria. In the grant application, which I sent to the
Mayor and Water Committee, I sent documentation of our efforts in trying to
reach the 70% water accountability threshold, Health Department correspondence
to that end and our water loss history for the previous twelve months I also documented
the test results from our Engineering Department using both two gallon and six
gallon per minute flow on ten randomly selected meters. This test showed an
average inaccuracy of those meters at a 23.5% loss to the town. I then
extrapolated the revenues we could fairly capture using that additional
percentage on top of our expected $2,300,000 water and sewer revenues when the
five year program is completed.
I was pleasantly pleased to be
receiving this money because I was not very hopeful we would be funded for this
project. I felt that if other applications from around the PDC came in that
were for projects that offered water and sewer services that was not already
then we would not be funded. However, we were.
This will be the fourth time we have
been funded from the Mt Rogers Program. The first was in 2004 when we received
$100,000 for the Water Treatment Plant Upgrade. The second was in 2007 when we
received $41,422.26 for the Paxton Lane / Washington Avenue Project that put
12 inch encasement with eight and two
inch water under I-81 (the county kicked in $34,670).
The third award was this year when we
were notified we will be receiving $100,000 on the sewer treatment plant
projects (which we have not received at this writing but will soon).
Situation on Sewer Treatment Plant
(STP) Digester Project
The bids came in on the STP Digester Co
Generation Project on August 31 and were way over budget. Thompson and Litton
had estimated the base bid to be in the $818,000 range and the low bid came in
at $1,076,000. There were only two bidders on the project – Waco, Inc. and Frizzell
Construction. However, at the pre bid conference there were at least five
general contractors and at least two subcontractors in attendance.
I am very concerned about this project.
This project started as a $500,000 project with a $250,000 grant and a $250,000
no interest 20 year loan when the project was presented to me in 2010. Sometime
in late 2010, in December I believe, Thompson and Litton approached me and said
the project was under budgeted and said another $409,535 would be required for
the project to make it a $909,535 one. I contacted the Department of
Environmental Quality and they agreed to allocate that additional money through
a no interest
loan. They presented the new figures to Council. For that meeting, they revised
their Preliminary Engineering Report (PER) to show still a net cost savings to
the town of approximately $10,703 per year ($43,680 in savings for oil and
electricity; $32,976.75 to service the loan). This scenario did not include
yearly maintenance costs which we estimate to be in the $3,500 to $5,000 range.
As stated above, the August 31 bid
came in at $1,076,000 or about $166,435 over the December 2010 new estimate.
With that amount I believe we have met or exceeded the cost benefit to the
town. I have asked Brian Tew of T&L to stop any additional engineering work
until the project can be brought into budget. I have asked them to consider any
number of options to that end including, but not limited to: scaling the
project back while retaining its green project grant status, getting more grant
money from the state, rebidding the project and advertising more widely, etc.
etc.
I have asked T&L to come up with
some contingencies to address these issues and bring the project back to
budget. I have asked them to give me a suitable date before the end of the
month so these issues can be addressed with the Sanitation and or Finance
Committees.
Contract With
District III Governmental Cooperative as it relates to the W. W. Scott, Jr.
Senior Citizens Center (SCC)
You have in your agenda packet an
agreement entitled “Memorandum of Agreement on Use of Designated Area Within
W.W. Scott Senior Citizens Center” That agreement is one of three that with
have District III Governmental Cooperative. The other two are a Site Control
Agreement where we historically receive $120 per month that basically helps
cover utilities, and a Site Management Agreement that basically helps covers
having a qualified person being over the nutrition Site at $350 per month. The agreements are for the October 1 through
September 30, which I assume coincides with the federal fiscal year.
Concerning the first agreement, Use
of Designated Areas, the Town and District III agreed around 2003 or 2004 to
revamp this agreement. Before that time the town was paid a nominal fee for the
use of the kitchen. After that time we agreed to prorate fees incurred by the
town on a 50% / 50% basis with District III. For instance, if repairs or
replacement in the kitchen were made for sinks, refrigerators, freezers, etc.
came to $5,000 during a particular fiscal year, that one half of that cost, or
$2,500, would be allocated the following fiscal year to District III in monthly
payments of $208.33. We set this system
up because we did not think it should be the town’s sole responsibility to
incur all the depreciation and replacement costs. This was especially so since
District III cooks all of their meals at the center and serves them throughout
the Mt. Rogers Planning District. The proportion served to Marion area seniors
is very low.
As you are aware, the town had to do
major repairs on the kitchen in May, June and July. The Kitchen was shut down
for much of that time. As you can see on
the attached sheet we incurred $14,461.32 in direct costs and another $7,716 in
labor costs, of which all was of our staff. While the contract itself is
somewhat nebulous on what constitutes a capital cost that can be split, I think
at very least that the one half cost of $7,230.66 per year or $602.55 should be
allocated to District III.
Equipment Committee Recommendations
on Snow Equipment
Included in your agenda packet is a
handwritten sheet giving the September 6 bid results on the four pieces of snow
equipment listed for the 2011-12 budget. They are for
a 10 foot salt spreader, a 10 snow plow, an 8 foot salt spreader and an 8.5
foot snow plow.
The bids were very close and the
committee and staff recommend purchasing the 10 foot snow plow from Richmond
Machinery in Richmond, the 10 foot salt spreader, the 8 foot salt spreader and
the 8.5 foot snow plow from Mid – State Equipment in Buchanan. These
recommended selections were either because of the low bids or they were for
equipment that best matches what we have now, namely for Henderson Spreaders.
Concerning the 8.5 foot snow plow, we think the Mid-State bid for the Western
plow is a more heavy duty plow and more suitable
for us.
By matching existing equipment with the
new equipment allows us more familiarity in operations, as well as the ability
to interchange parts. Additionally, the total bid price is $28,580 is well
under $39,000 in the budget.
Respectfully Submitted,
John E. B. Clark, Jr.
Town Manager